Schedule E Calculation of Estimated Property Tax for Relevant Hospital Entity Attach to Form PTAX-300-H Step 1: Describe the property Use of property 1 Address 2 Property index numbers 3 Step 2: Provide the estimated land value 4 Total assessed land value Step 3: Figure the estimated buildings value 5 Square footage of building 6 Marshall & Swift x x x x x Cost Manual x x 7 Total replacement cost = = = = = = = 8 Actual age 9 Adjusted remaining life 10 Percentage of remaining life x . ___ ___ x . ___ ___ x . ___ ___ x . ___ ___ x . ___ ___ x . ___ ___ x . ___ ___ 11 Assessment factor x x x x x x x 12 Assessed buildings value = = = = = = = Step 4: Figure the total estimated assessed value 13 Land value (Line 4) 14 Buildings value (Line 12) + + + + + + + 15 Total estimated value = = = = = = = Step 5: Figure the total estimated property tax 16 Add all Line 15 totals together. 16 ________________ 17 Multiply Line 16 by the state equalization rate: ___________ 17 ________________ 18 Multiply Line 17 by the applicable tax rate: ___________ Write this amount on PTAX-300-H, Line 19. 18 ________________ = Page 1 = Instructions for Schedule E example, a hospital with a remaining life of 28 years is Step 2: Provide the estimated assessed divided by a 40 year useful life to obtain a percentage land value of 70%. Line 4 – Total assessed land value - Determine Line 11 – Assessment factor – Write the assess- a square foot average of assessed values of three ment factor for the county. parcels of land (not including farm land, and excluding the assessed value of the improvements thereon) that Line 12 – Estimated assessed buildings value – are reasonably comparable to the property. Multiply Multiply Line 7 by Line 10 by Line 11. this average by the square foot of land for which the exemption is sought. Step 4: Figure the total estimated as- sessed value Step 3: Figure the estimated buildings value Follow the instructions on the form. Line 5 – Square footage of building – Calculate the Step 5: Figure the total estimated prop- square footage of the building for which the exemption erty tax is sought. Follow the instructions on the form. Line 6 – Marshall & Swift Cost Manual – Calculate the replacement cost per square foot for Class A Aver- age building found in the most recent edition of the Marshall & Swift Valuation Services Manual, adjusted by any appropriate current cost and local multipliers. Line 7 – Total replacement Cost – Multiply Line 5 by Line 6 to obtain an estimated replacement cost of building. Line 8 – Actual Age – Write the actual age of the building. Line 9 – Adjusted Remaining Life – The useful life of a building is a weighted mean life based on origi- nal construction. Hospitals are assumed to have a 40-year life and other types of buildings will use the applicable life from the American Hospital Association publication “Estimated Useful Lives of Depreciable Hospital Assets”. Hospital buildings older than 35 years will have an assumed remaining life of 5 years and hospital buildings newer than 8 years will assume to have a remaining life of 32 years. Apply the same parameter ratios of remaining life to non-hospital buildings. Line 10 – Percentage of remaining life – The ad- justed remaining life is divided by the useful life. For = Page 2 =